Mt Mercer wind farm

Mt Mercer is a 64-turbine wind farm near Ballarat in Victoria, Australia.

Mt Mercer is the second wind farm Meridian has constructed in Victoria and will make a substantial contribution to Australian retailers meeting their commitments under the Australian Renewable Energy Target scheme.

Building Mt Mercer

Work on Mt Mercer started in December 2012 and was completed in December 2014. It was developed by Meridian Energy Australia, a wholly owned subsidiary of Meridian Energy Ltd. Construction partners were: REpower Systems SE for wind turbines and Downer EDI for civil works.

The wind farm is connected to the Victorian Electricity Grid by a new powerline and green field terminal station near the town of Elaine. This connection is built, owned and operated by Transmission Operations (Australia) (Powercor/Citipower).

First power was generated to the grid mid-November 2013.

Key dates

  • Dec 2012
    Construction begins
  • Nov 2013
    First power generated
  • Dec 2014
    Mt Mercer fully operational

 