The project site is a 1,022ha dairy farm located in Rangitāiki, southeast of Taupō. It’s being completed in two stages, each involving the construction of a 200MW solar plant. Stage one is under construction, and stage two is consented but subject to Board approval. Offtake will be shared 50-50 between Meridian and Nova.
Stage one construction
Enabling works began on stage one of Te Rahui in early 2025, with construction beginning in earnest in early 2026.
Commissioning of the solar farm is expected to begin in 2027.
Substation
Construction of the solar farm substation – a key part of the infrastructure that connects a solar plant to the electrical grid – is also underway.
The substation is expected to be completed and connected to the national grid by late November 2026.